Bluewave

For this project we started off doing excavation for catch basin’s and poured concrete pads for truck load outs and off loads. Once this was completed we made a pre-cast concrete containment with a very low tolerance gravel pad to carry 8 bulk tanks for various fuels; this was incredibly challenging due to the winter conditions. We managed to achieve the approved grading compaction and moisture tests.