Ace Shop
Location: Fort St. John, BC
Scope: Building 5 precast panel shops
Time frame: 5 months
AltaGas
Scope: LNG spill containment pit
Time frame: 1.5 months
Bear Mountain
Scope: Refurbish ski chalet deck
Time frame: 3 months
Bluewave
Location: Dawson Creek, BC
Scope: Concrete pads and pre-cast concrete containment
PerCon
Scope: Over 300 lineal ft of grade beam and created pilaster boxes
DiCorp
Scope: Concrete pads and rebar cages
Medicine Hat Substation
Scope: Sono tubes and bolt patterns for electrical towers
Pembina
Scope: Epoxy grouting of pump pads
Time frame: 4 months
Swamp Donkey
Scope: 30 ft concrete vault for valves and pumps
Time frame: 1 month
Gold Creek
Scope: Frac Sand Facility
Time frame: 7 months
Hospital Parkade
Location: Grande Prairie, AB
Scope: Concrete
Time Frame: Ongoing…
Big Molly
Location: Glenevis, AB
Scope: Frac Sand Facility
Time Frame: 8 months
Wahleach Fire Protection Tank
Location: Hope, BC
Scope: RTP Liquid Tank
Time Frame: 1 month